Murray State University School of Engineering CourseWiki

Bills of Materials

List the parts in an assembly and estimate each part's material share without confusing stock purchases with per-part consumption.

A bill of materials says what goes into one assembly

A bill of materials says what goes into one assembly

A bill of materials (BOM) lists the parts needed for a product. Give each part a stable number, a clear name, a quantity per assembly, a material and a make-or-buy designation. Identify the stock for made parts and the purchasing description for bought parts.

Made means the part needs a drawing and a route such as an operation method sheet. Bought means it arrives as a component; it still needs a size and specification so the buyer can obtain the correct item. Match the BOM revision to the assembly drawing. State whether quantities are per assembly or for the whole batch.

Material cost per part is its allocated stock share times stock price

Material cost per part is its allocated stock share times stock price

Estimated material cost per part = stock share allocated to that part × price of that stock unit. Keep both amounts on the same basis: length for constant-section bar, area for sheet of the same thickness, or mass when purchased by mass.

Allow for the saw cut's width (kerf), trimming and unusable stock. Finished-part volume alone can understate what making the part consumes. State how you allocate waste and reusable leftovers so two estimates can be compared.

Consumption, purchase cost and batch yield answer different questions

You may need to buy a whole sheet even when one part uses a small fraction. That purchase is a cash requirement; the allocated fraction is the material estimate for the part. For a batch that consumes the entire stock unit, dividing its cost by the number of acceptable parts includes the loss from rejected pieces. Avoid charging the same waste once in the allocated share and again as an added allowance.

Worked BOM: one display label assembly costs $1.20 in allocated materials

Worked BOM: one display label assembly costs $1.20 in allocated materials

This original example matches DL-01 in Operation Method Sheets and Critical Dimensions for the Shop. All prices are invented teaching values, not quotations. Assembly DL-A, revision A, contains one made plywood plate and two purchased closed cord loops.

The 110 × 50 × 6 mm starting blank is allocated a 120 × 60 mm area of a 1200 × 120 × 6 mm birch plywood strip costing $18. The larger allocation includes room for cutting and trimming. Allocation share = (120 × 60) / (1200 × 120) = 0.05. Plate material estimate = 0.05 × $18 = $0.90.

DL-A revision A — quantities and material estimate per assembly
Part number / nameMake / buy; material and stockQuantityCost eachExtended cost
DL-01 / display label plateMake; birch plywood, blank 110 × 50 × 6 mm; allocated stock area 120 × 60 mm as above.1$0.90$0.90
DL-02 / closed cord loopBuy; waxed cotton cord, 1 mm diameter, 100 mm closed-loop circumference; example pack of 20 for $3.2$0.15$0.30
Total allocated material and purchased-component cost per assembly$1.20

Extended cost is quantity × cost each. The $1.20 excludes labor, machine time, tooling, consumables, taxes and delivery. It is not a complete manufacturing cost or a selling price. Broader cost roll-up and design-for-manufacturing decisions belong with manufacturing economics.

Buying one strip and one pack costs $21, even for one assembly. Unused material remains inventory; do not confuse that purchase total with $1.20 of allocated consumption.

Check quantities, units and waste before totaling the BOM; Checklist; Practice

Check quantities, units and waste before totaling the BOM

  • Match every drawing part number to a BOM row.
  • State the quantity per assembly and multiply once for the batch quantity.
  • Specify stock dimensions and material for made parts, and purchasing details for bought parts.
  • Use the same units in the stock-share numerator and denominator.
  • Document the cutting allowance and treatment of leftovers.
  • Multiply each quantity by its unit cost and sum the extended costs.

Keep unrounded intermediate calculations; round money to cents at the stated reporting step.