Compare casting, bulk deformation, sheet forming and powder metallurgy by shape, material, tooling and production quantity.

Choose the shape-making route before comparing production cost; Checklist

Choose the shape-making route before comparing production cost

Metal parts can begin as liquid poured into a mold, solid stock plastically deformed into a new shape, or powder pressed into a compact. Plastic deformation means a permanent shape change after the force is removed. Each route limits the shapes it can make and the tools it needs. A die is a tool that controls shape; a mold contains material while it takes shape.

These shape-making routes sit under Forming in the classification used by Manufacturing Process Categories. In metalworking references, forming often means solid-metal deformation specifically, with casting listed separately. Cutting is Separating; joining is Fabricating; property-changing treatment is Conditioning; surface protection or appearance is Finishing. Metals are one of the four families in Material Families, alongside Plastics, Wood & Composites, and Ceramics & Glass. Metal properties and heat treatment are separate topics.

  • Identify the alloy, overall shape, holes and thin regions.
  • State the quantity and whether the design will change.
  • Check tool access and how the part will leave the mold or die.
  • Compare tooling cost, repeatability and production rate.
  • Allow for trimming, machining, joining and finishing afterward.
Casting makes a shape by solidifying metal inside a mold

Casting makes a shape by solidifying metal inside a mold

Three casting routes and their trade-offs
RouteHow it worksTypical products and cost trade-off
Sand castingA pattern makes a cavity in bonded sand. Remove the pattern, assemble the mold, pour metal, then break away the mold after solidification.Pump housings and large machine bases. Relatively flexible tooling can suit small batches; making a new mold for every part adds work.
Investment castingA disposable pattern, often wax, receives a ceramic shell. Remove the pattern and fire the shell before pouring metal. Break away the shell afterward.Detailed brackets, valve parts and turbine components. Fine detail can reduce later machining, but pattern and shell preparation add time and cost.
Pressure die castingInject molten metal into a reusable metal die, let it solidify, then open the die and eject the part.Repeated aluminum or zinc housings. Expensive dies and equipment can pay off over long runs; alloy, size and geometry must suit the process.

There is no universal quantity at which die casting becomes cheapest. Obtain estimates for the actual geometry, alloy, tool life and required secondary operations.

Supporting detail: Addendum 1 — Sources for the casting routes.

A casting needs room to release, shrink and feed

A casting needs room to release, shrink and feed

Schematic sand mold with the cope above the drag, a sprue and runner feeding the cavity, a riser above it and a supported core forming an internal opening.

The cope is the upper mold half; the drag is the lower half. The sprue leads downward from the pouring opening, and a runner and gate lead into the cavity. A riser supplies liquid metal as the casting solidifies and contracts. A core occupies space that must remain hollow.

Draft is a slight taper that helps a pattern or casting leave its tooling. A shrinkage allowance changes tooling dimensions to account for contraction. Neither is a universal number: alloy, geometry and process matter. Critical faces or holes may need machining afterward.

Supporting detail: Addendum 2 — Why a larger pattern does not replace a riser.

SFSA explains riser feeding and shrinkage voids.

Rolling squeezes, forging compresses and extrusion pushes through a die

Rolling squeezes, forging compresses and extrusion pushes through a die

Side-by-side sketches: rolling reduces stock thickness between rolls; forging compresses stock between dies; extrusion pushes a billet through an opening into a long profile.

Solid-metal forming routes
RouteShape and examplesTooling and quantity
RollingRotating rolls reduce thickness or produce a section. Sheet, plate and structural shapes are common products.Large equipment investment suits substantial throughput; a designer can often buy standard rolled stock.
Open-die forgingDies compress a solid workpiece without enclosing its whole outline. Examples include large shafts and rings.Relatively simple dies accommodate varied sizes; repeated positioning and later machining may be needed.
Closed-die forgingShaped die cavities guide metal flow into repeated parts such as connecting rods and wrenches.Dedicated tooling favors repeated production. Excess metal may form flash that is trimmed away.
ExtrusionA ram pushes a billet through a die opening. Long channels, rails and heat-sink profiles have a substantially constant cross-section.A dedicated profile die can serve many lengths. Cut ends, cross holes and local pockets require later operations.
Wire drawingPull wire through a reducing die to make it thinner and longer. This is different from pushing stock through an extrusion die.Die sets and handling equipment suit repeated lengths; several reductions may be needed.

Hot working occurs at temperatures and deformation rates that allow recrystallization, the formation of new grains, during deformation. Cold working occurs where that process does not remove the work hardening as deformation proceeds. The boundary depends on the metal and processing conditions; it is not one temperature for every alloy. Hot rolling permits large shape changes, while cold rolling commonly improves dimensional control and surface quality and can increase strength through work hardening.

Supporting detail: Addendum 3 — Cold forming does not guarantee an unchanged dimension.

Supporting detail: Addendum 4 — Sources for solid-metal deformation.

Sheet forming changes shape; blanking and shearing separate material; Practice

Sheet forming changes shape; blanking and shearing separate material

Bending changes the angle of sheet, as in a bracket or enclosure. A press brake uses a punch and die to make bends; adaptable tooling suits prototypes and short runs. Roll forming progressively bends strip through roll stations into a long profile, such as a channel. Its dedicated roll tooling favors repeated lengths. It is different from rolling sheet thinner.

Deep drawing pulls sheet from a flat blank into a die cavity to make a cup or shell. Tooling must control material flow to limit tearing and wrinkling. Dedicated tools suit repeat production. This is different from pulling wire through a reducing die.

Stamping names a press-based production route that can combine several operations. Bending and drawing are Forming; shearing and blanking are Separating. In blanking, the cut-out piece is the wanted blank; in punching a hole, the removed slug is usually scrap. A stamping line can therefore perform more than one process category.

Bend allowance accounts for the material length within a bend when developing a flat pattern. The sheet stretches on the outside and compresses on the inside. Use a validated bend table or supplier data for the alloy, thickness, radius and tooling; adding outside leg dimensions alone does not give the correct blank length.

Practice selecting a sheet process

Supporting detail: Addendum 5 — Sources for sheet forming and flat patterns.

Powder metallurgy presses particles, then bonds them by sintering

Powder metallurgy presses particles, then bonds them by sintering

In conventional press-and-sinter powder metallurgy, powder fills a die and is compressed into a green compact: a shaped part that is not yet fully bonded. Heating then bonds the particles during sintering, generally without melting the main metal throughout. Some systems include a liquid phase.

Small gears and porous bearings are typical products. Dedicated dies and presses favor repeat quantities and can produce a near-net shape, close to the finished dimensions. Tool access, ejection and density variation limit geometry; critical features may still require sizing or machining.

Supporting detail: Addendum 6 — Porosity can be useful or unwanted.

MPIF explains conventional compaction, sintering and secondary operations. This section describes that route, rather than every process that begins with metal powder.

Plan the separating operations that finish the geometry

Plan the separating operations that finish the geometry

Follow Milling Operations for machined faces and pockets, Lathe Operations for turned features, and Feeds and Speeds for cutting-data concepts. Use Tolerances and Fits to decide which dimensions require close control and Surface Texture and Finish to distinguish a surface requirement from a process name.

Forming is often only the beginning of a route. A casting can be machined, joined and coated. These pages compare processes for design; operating procedures belong in Equipment Operating Procedure and Machine Hazards and Housekeeping.

Materials and Manufacturing Processes/Metals

Joining Metal

Compare welding, brazing, soldering and mechanical assembly by joint access, heat input, production needs and service requirements.

Choose a joint around its load, access and need for disassembly

Choose a joint around its load, access and need for disassembly

Joining parts is Fabricating. First identify the metals, thicknesses, loading, service environment and whether the assembly must come apart. Then check access for the joining equipment and for inspection.

A welded frame can avoid a large casting tool, but fit-up, fixtures and inspection still cost money. A bolt-on cover allows service access, but needs clearance for the fasteners and tools. See Fasteners and Galvanic Corrosion for mechanical assembly.

This is a process-selection overview. For safety requirements, use Personal Protective Equipment, Fire Safety, Chemicals and Safety Data Sheets and Equipment Operating Procedure.

Welding joins the base metal; melting is not required in every process

Welding joins the base metal; melting is not required in every process

Fusion welding melts base metal at the joint, with or without added filler metal. The pool solidifies to form the joint. The common arc, oxy-fuel and resistance spot processes below are fusion processes.

Solid-state welding forms a bond without bulk melting of the base metals. Friction welding is one example. A solid-state process can still heat and alter nearby metal; “not melted” does not mean “unchanged.”

The heat-affected zone is nearby base metal whose structure or properties change because of the thermal cycle, without itself becoming weld metal. Selecting a process includes checking those changes and distortion, not merely whether a bead looks smooth.

Supporting detail: Addendum 7 — Sources for fusion welding, solid-state welding and the heat-affected zone.

Compare the heat source, filler and access of five welding processes; Practice

Compare the heat source, filler and access of five welding processes

Comparison of oxy-fuel, stick, MIG, TIG and resistance spot welding by heat source, filler supply and typical application.

Starting candidates for process selection
ProcessHow it works and where it fitsTrade-off
Oxy-fuel weldingA fuel-and-oxygen flame heats the joint; a separate filler rod may be added. Oxyacetylene can suit selected thin-steel work and repair.Flexible equipment, but slower and with more broadly distributed heating than many production arc processes.
SMAW / stickAn arc melts a flux-coated consumable rod. The coating supplies protection for the weld pool. Common for steel repair and construction work.Portable equipment and flexibility; rods need replacement and slag needs removal between appropriate stages.
GMAW (MIG/MAG)An arc melts continuously fed wire under external shielding gas. Common for repeated steel or aluminum fabrication with suitable wire, gas and settings.Continuous wire supports production and automation; shielding and equipment access must suit the job.
GTAW / TIGAn arc from a non-consumable tungsten electrode heats the joint under inert gas. Filler, when needed, is supplied separately. Useful for controlled joints in thin stainless steel and aluminum.Good control of heat and filler, but often slower than wire-fed production welding.
Resistance spot weldingOpposed electrodes press overlapping sheets together and pass current through them, forming a local fused nugget. Common in repeated sheet assemblies.Rapid repeat joints with suitable equipment and fixtures; conventional arrangements require access to both sides. Separate spots do not make a sealed seam.

Supporting detail: Addendum 8 — Why MIG is a familiar name but GMAW is the broader term.

Supporting detail: Addendum 9 — Sources for the five process mechanisms.

Practice choosing a joining method

Brazing and soldering melt filler while the base parts stay solid

Brazing and soldering melt filler while the base parts stay solid

In brazing and soldering, a molten filler wets the solid base parts. In a suitable close-fitting joint, capillary action draws filler into the gap. The usual dividing temperature is 450°C: the American Welding Society describes brazing fillers as having a liquidus above 450°C and soldering fillers below it. Liquidus is the temperature above which the filler is fully liquid. This distinction concerns the filler, not the flame temperature or the machine's setting. In both processes the base parts remain solid. Neither is simply a cooler version of fusion welding.

Brazing can join suitable dissimilar metals or attach a carbide tip to a steel tool body. Soldering is common in electrical connections. Choose filler and joint design for compatibility, temperature and loads; a soldered electrical connection is not automatically suitable for a structural load.

Joint clearance, surface condition and heating method matter. Brazing can be manual or performed in production equipment such as a furnace. Mechanization changes throughput and tooling costs; the process name alone does not identify the cheapest route.

Supporting detail: Addendum 10 — Sources for the filler-temperature distinction and capillary joint.

Specify the required joint, not just the name of the machine; Checklist

Specify the required joint, not just the name of the machine

  • Identify both base materials, thicknesses and any coatings.
  • Describe the joint location, overlap or preparation and equipment access.
  • State load, leak-tightness and appearance requirements.
  • Allow for distortion, inspection and any later machining.
  • Coordinate the finish and any assembly sequence constraints.

A drawing and its referenced specification communicate the required weld and acceptance criteria. A process abbreviation alone does not specify weld size, extent or quality. Likewise, a visually neat joint does not establish internal soundness. Heat-treatment selection is a separate topic.

Materials and Manufacturing Processes/Metals

Fasteners and Galvanic Corrosion

Choose mechanical joints for service access, thread compatibility and exposure to moisture and dissimilar metals.

Match the fastener to the assembly and its service access

Match the fastener to the assembly and its service access

Common mechanical joining components
ComponentPurposeDesign check
Bolt and nutProvide a removable threaded connection that can clamp parts together.Provide tool access, suitable thread engagement and a compatible strength and material specification.
WasherProvides a bearing surface or distributes load where the design requires it.A plain washer does not by itself prevent loosening or electrically isolate an entire joint.
RivetForms a retaining head through permanent deformation.Suitable for repeated sheet assembly; removal normally destroys the rivet. Blind rivets permit installation from one side.
Threaded insertProvides an internal thread in a host part.Select an insert designed for the host material and thickness. Check installation access, pull-out and resistance to rotation.

Standard fasteners often reduce dedicated tooling for short runs, but every fastener adds parts and assembly time. Riveting or automated fastening may suit long runs. Removability, inspection and repair can justify a threaded joint even when another method is faster.

A thread size alone does not specify a complete fastener; Practice

A thread size alone does not specify a complete fastener

The mating threads must agree in diameter, spacing and thread system. Similar-looking inch and metric parts are not interchangeable. Pitch describes axial spacing between adjacent thread forms; threads per inch describes a count over a unit length.

A purchase or drawing specification also needs the relevant length, head style, material or strength grade, coating and thread-fit requirements. The wrench size is not the thread diameter. Use the applicable thread reference and supplier drawing to decode a designation before choosing mating parts.

Read diameter and thread spacing separately
ExampleDiameterSpacing and system
1/4-20 UNCNominal thread diameter: 1/4 inch.20 threads per inch; UNC is the Unified coarse series. The pitch is 1/20 inch, not 20 inches.
M6 × 1Nominal metric thread diameter: 6 mm.Pitch: 1 mm between corresponding points on adjacent threads. The 1 is not a count of threads per inch.

These are thread-size examples, not complete fastener specifications. Nominal diameter identifies the size; tolerances govern the actual mating dimensions. A 1/4-20 thread and an M6 × 1 thread differ in both diameter and spacing.

Supporting detail: Addendum 11 — Sources for thread names and size examples.

Practice decoding a thread designation

For dimensional fit concepts, see Tolerances and Fits. For a permanently joined alternative, see Joining Metal.

Galvanic corrosion needs a metal pair, electrical contact and an electrolyte

Galvanic corrosion needs a metal pair, electrical contact and an electrolyte

Dissimilar metals can form a corrosion cell when they are electrically connected and share a conductive liquid, called an electrolyte. Moisture containing salts can provide that liquid. The more active member of the pair acts as the anode and may corrode faster; the other acts as the cathode.

A wet joint connects a more active metal to a more noble metal, completing a corrosion cell. A second sketch shows an insulating sleeve and washers separating a fastener from the surrounding plate.

A galvanic series ranks metals by their behavior in a specified environment. It helps screen combinations; it does not predict a service life. Alloy condition, surface films, wetting and exposed areas matter. A dry pair is not automatically a working galvanic cell.

Supporting detail: Addendum 12 — Why the wetted areas matter.

Supporting detail: Addendum 13 — Sources for galvanic contact, coatings and area effects.

Review the complete joint before calling a fastener compatible; Checklist; Practice

Review the complete joint before calling a fastener compatible

“Stainless” does not mean compatible with every metal, and a coating is not a permanent guarantee of isolation. Consider material pairing, durable electrical separation, drainage and a suitable protective finish together. An insulating washer under a head does not isolate a shank that still touches the hole wall.

  • Identify the base metal, fastener, washer and their coatings.
  • Identify where electrical contact and moisture can occur.
  • Check the material pairing for the actual service environment.
  • Review sleeves, washers or gaskets for complete isolation and mechanical suitability.
  • Provide drainage and an inspectable, maintainable finish.

Compatibility review does not replace structural sizing or joint design.

Practice spotting a corrosion risk

Supporting detail

Addendum

Additional evidence, standards context, and background referenced from the main text.

  1. Materials and Manufacturing Processes/Metals/Forming Metal

    Addendum 2. Why a larger pattern does not replace a riser

    Pattern allowance addresses final size. Feeding addresses a different problem: a solidifying region may need more liquid metal to avoid an internal shrinkage void. A riser must remain able to feed that region. The diagram identifies parts of a mold, not a production gating design.

    Back to reference 2

  2. Materials and Manufacturing Processes/Metals/Forming Metal

    Addendum 3. Cold forming does not guarantee an unchanged dimension

    Cold forming generally requires greater force than comparable hot forming. It avoids a separate hot-working step, but that does not prove every production cycle is faster. Springback, residual stress and later processing can change dimensions. Forging can also be hot, warm or cold; heat is not part of its definition.

    Back to reference 3

  3. Materials and Manufacturing Processes/Metals/Forming Metal

    Addendum 4. Sources for solid-metal deformation

    The Forging Industry Association's Forging 101 (PDF) compares open- and closed-die processes and hot, warm and cold forging. Queen City Forging explains recrystallization and temperature classification. A Dartmouth-hosted metal-forming case study compares rolling, forging and drawing regimes. The Australian Aluminium Council's Extrusion Manual (PDF), page 10, explains flow through a die into a uniform section. Contenti's wire-drawing explanation (PDF) identifies pulling through progressively smaller openings; its operating steps are outside this selection overview.

    Back to reference 4

  4. Materials and Manufacturing Processes/Metals/Joining Metal

    Addendum 8. Why MIG is a familiar name but GMAW is the broader term

    MIG refers to metal inert gas welding. GMAW also covers processes using active shielding gases or mixtures, often called MAG. Gas and filler selection depend on the alloy and process; the familiar shop name is not a complete welding specification.

    Back to reference 8

  5. Materials and Manufacturing Processes/Metals/Fasteners and Galvanic Corrosion

    Addendum 11. Sources for thread names and size examples

    McMaster-Carr explains inch diameter/TPI and metric diameter/pitch, including M6 × 1. Its UNC catalog identifies 1/4-20 as UNC. NASA's Fastener Design Manual (PDF), printed pages 12–13 / PDF pages 16–17, explains Unified coarse/fine series and thread classes. The manual is background on thread terminology, not a current procurement specification.

    Back to reference 11

  6. Materials and Manufacturing Processes/Metals/Fasteners and Galvanic Corrosion

    Addendum 12. Why the wetted areas matter

    A small active area coupled to a large noble area can suffer concentrated attack when both areas contact the electrolyte. That is why coating only the active member is not automatically a cure: a small defect in that coating can leave a small wetted anode coupled to a large cathode. The relevant areas are those participating in the wet corrosion cell, which can change as a joint dries. A compatibility decision must consider the complete joint and environment.

    Back to reference 12